Federal regulators observe Vogtle Unit 3's liquid processing tanks inside the reactor building in Georgia. Nuclear Regulatory Commission / Flickr

By Jessica Corbett

Georgia's public utility commission voted 5-0 on Thursday to continue construction on two half-finished nuclear reactors that will cost an estimated $25 billion, even though the project is now "more than $10 billion over budget and five years late."

Opponents of nuclear power were disappointed by the unanimous decision, which the Wall Street Journal noted was considered "a victory for Southern Co., whose subsidiary Georgia Power is the primary owner of the Alvin W. Vogtle Electric Generating Plant, which has two existing reactors." The project has faced opposition from local residents as well as national groups that emphasize the long-term risks of nuclear power.